Heating and cooling upgrade works

As part of the university’s commitment to its people and the student experience, we are continuing to improve our spaces on campus with an upgrade of heating and cooling systems.

Upgrades to heating and cooling in Hawthorn, Croydon and Wantirna

To improve student and staff comfort levels, we are upgrading heating and cooling systems with new or enhanced infrastructure in several buildings across all three campuses.

Buildings to receive upgraded infrastructure –

Hawthorn

Buildings TA and TB

Building Commences* Finishes*
TB - level 2 - Room TB222, TB223, TB224 & TB221 29/01/2020 21/02/2020
TB - level 3 - Room TB302, TB303 & TB305 29/01/2020 21/02/2020
TB - level 3 - Room TB310, TB311, TB311a, TB312, TB313, TB315, TB318, TB319, TB321 & TB350 21/02/2020 17/03/2020
TB - level 3 – Room TB314, TB316, TB317, TB320, TB322 16/03/2020 03/04/2020
TA - level 3 - Room TA301, TA302, TA304, TA302a, TA304, TA305, TA303,TA303a, TA303b, TA308, TA309, TA311 & TA308a 29/01/2020 21/02/2020


Croydon

All buildings except CN1 and CN4.

Building Commences* Finishes*
CT - level 1 - Room CT102 & CT101 03/02/2020 17/02/2020
CT - level 2 - Room CT201 17/02/2020 21/02/2020
CT - level 3 & Roof Platform - Room CT401 & CT301 25/02/2020 27/03/2020
CH – level 1 – area 1- Room CH107, CH109 & CH110 30/03/2020 24/04/2020
CH – level 1 - area 2 - Room CH102, CH104, CH105 & CH106 27/04/2020 15/05/2020
CK - ground floor - Room CK102, CK103 & CK104 11/05/2020 01/06/2020
CK - level 2 - Room CK201, CK202 & CK203 01/06/2020 26/06/2020
CF - CF Roof Plant room 13/04/2020 01/05/2020
CF – level 1 – area 2 - Room CF102 04/05/2020 18/05/2020
CF – level 1 – area 3 - CF112 & CF101 18/05/2020 22/05/2020
CF - Area 4 - CF Roof Plant room 25/05/2020 05/06/2020
CF – level 1 - area 5 - CF114, CF113, CF113a & CF113b 10/06/2020 24/06/2020
CC - level 1 - area 1 - Room CC103 & CC107 22/06/2020 02/07/2020
CC - level 1 - area 2 - Room CC101 04/07/2020 10/07/2020
CC - level 2 - area 2 - Room CC201, CC203, CC205 & CC207 29/06/2020 10/07/2020
CC - level 2 - area 1 - Room CC204, CC202, CC206, CC211, CC210, CC209, CC208 & CC212 13/07/2020 04/08/2020
CE - level 1 - area 2 - Room CE102, CE104, CE106 & CE150 (Corridor) 30/03/2020 09/04/2020
CD – level 1- area 1 - Room CD151 & CD102 13/04/2020 01/05/2020
CD – level 1 - area 2 - Room CD101 04/05/2020 26/05/2020
CD – level 1 - area 3 - Room CD180 25/05/2020 26/06/2020

 

Wantirna

All buildings except WC, WM1, WM2, WM3, WM4, WM5, WM6, WM7, WM8, WM9, WN2, WN3, WL. Schedule release early 2020.

Duration of work

The project commenced in September and will continue until December 2020. Upgrades to TA and TB in Hawthorn are expected to be completed by May 2020. Work at Croydon is scheduled for completion by November 2020 and Wantirna upgrades to be completed by end of 2020.

Key changes during the project

  • Some areas within buildings will be temporarily closed off.
  • Where possible, we are working to relocate classes.
  • Increase in noise from building works.
  • Increased foot traffic with workers on-site.

More information

Please keep checking this website for updates on the progress of this improvement to our facilities.

We appreciate your patience and support during this infrastructure upgrade.